Skip to content

What counts in user efficiency ​

Where the numbers on Efficiency - User come from: which work counts as Technology time, which hours count as Presence, and what the page shows but does not count. How to use the page is in Check user efficiency.

1. Efficiency is technology time divided by presence ​

Efficiency = Technology time ÷ Presence × 100 %, and Efficiency with factor = Technology time ÷ Presence with factor × 100 % — the chart shows the one with factor. All are in hours, counted per person and per period (day, week, month, year or the whole period), and only for the days from From to To: work and presence on other days are left out, also with Interval: Full. A person with presence but no technology time, or the other way round, gets 0 %.

One bar per person and weekOne bar per person and week

2. Technology time: planned hours of finished work-order tasks ​

Technology time is the planned time of the work, not the time the clock ran:

  • Only tasks on work orders count, and only for technologies of type Start/Stop per piece. Other technology types and tasks that are not on a work order (meetings, clean-up, training — see the Other tab below) add nothing.
  • Each task adds technology time per piece × quantity of the work order item. Somebody who finishes faster than planned gets more than 100 %; slower, less.
  • The task must be completed: it needs both a start and a completion date, and must overlap the chosen period. A task still in progress counts once it is completed.
  • A task worked on by several people is split equally between everybody on the task. Only the people you selected are shown; the share of a colleague you did not select is not given to anyone else.
  • The hours land on the days the task was In progress and the person was present, in proportion to the time it spent in that status each day. A task left in progress overnight or over a weekend therefore puts no hours on days nobody was at work. Paused time does not move hours. A task without any In progress history counts on the day it was completed.

Hours per work order, and the task’s status history that spreads them over daysHours per work order, and the task’s status history that spreads them over days

Click a bar to see this list. Hours is what each work order added to the person’s technology time in that period; the arrow opens the task’s status history.

3. Presence: time between clock-in and clock-out ​

Presence comes from the Registration (clock-in / clock-out) events in HR attendance:

  • Every day, the registrations are paired in order — first with second, third with fourth — and the time between each pair is added up. A clock-in without a matching clock-out that day adds nothing.
  • Absences (sick leave, vacation and the other attendance types) are not presence: a day off lowers both presence and technology time, not efficiency.
  • Presence is calculated once a night, by default for the last 45 days. Today’s registrations and fresh corrections show up the next day; corrections older than that are not picked up.
  • It is calculated only for people with an active work position in their HR profile in that month.

4. Presence with factor, capacity and overhours ​

These come from the person’s own resource in Capacities (people without a resource get a factor of 1 and no capacity):

  • Presence with factor = presence × the resource’s Efficiency for that day in Capacities (or the resource’s default Efficiency when the day has none). It is the part of the presence that is expected to go into planned work — with 0.9, eight hours of presence count as 7.2 h.
  • Capacity is the hours planned for the resource on the chosen days in Capacities.
  • Overhours = Presence − Capacity. Negative means fewer hours at work than planned, for example a sick day.

A week with a sick day: less technology time and presence, negative overhoursA week with a sick day: less technology time and presence, negative overhours

5. Pause and Other: shown, not counted ​

The window behind a bar has two more tabs. Neither changes the efficiency; they help explain it.

Pause: time the listed work orders spent paused, per reasonPause: time the listed work orders spent paused, per reason

Pause adds up the time the listed work orders spent in a status with a pause reason (a tag such as Waiting for material). The person is usually still at work then, so long pauses mean presence without technology time.

Other: tasks that are not on a work orderOther: tasks that are not on a work order

Other lists the person’s tasks that are not on a work order and started or finished in that period. Their time is not technology time, but it is presence — which is why a week full of meetings shows a lower efficiency.

6. Target, totals and averages ​

  • Target percentage only draws the red line. With Calculate percentage based on target ticked, the chart’s efficiency is divided by the target, so a person exactly on target shows 100 %. The table and the CSV are not affected.
  • In the table, Average is the average of the periods that have a value; empty periods are skipped. The Total row adds up the hours, but its efficiency columns are the average of the people, not total technology time ÷ total presence.
  • With Split by user off, the chart shows one bar per period: total technology time ÷ total presence with factor of everybody. That can differ from the table’s Total row.